How to structure a construction payment schedule
Keep payments ahead of your costs. The goal is to never be carrying much of the job on your own cash. Put big payments right before or right after big material purchases, like cabinets, windows, or shingles.
Use milestones anyone can check. "Rough plumbing inspection passed" is clear. "50% complete" invites an argument. Clear milestones mean the client knows exactly when a payment is due.
Hold a meaningful final payment. A final payment of 10–15% gives the client confidence you'll finish the punch list, which makes the rest of the schedule easier to agree to.